Ontario's electricity sector experienced more of the same during the first half of the year - which continues to betray the ongoing mistakes of the government and the Ontario Power Authority (OPA).

With supply mix issues in the forefront, including the demon wind and the sale/disposal of AECL this week, I thought I'd review what the supply mix actually was, in terms of production, over the first half of this, and past, years. The quick visuals show that the big growth stories (since 2004) have been nuclear, and natural gas - with coal the obvious target of reductions.
The government has been fairly consistent in noting a desire for about 50% of the supply being provided by nuclear power. The supply mix I've shown is production, which includes electricity that gets exported. In the first half of 2011, nuclear power generated about 42.5 TWh of electricity, and Ontario consumed about 70.2 TWh - so nuclear production was over 60% of Ontario consumption. I am a strong supporter of nuclear, and I invite readers to view Donald Jones' Alternative Long-Term Energy Plan, but currently only 2 reactors at Bruce B are consistently used in demand response actions by the IESO. There is a flexibility issue with output from our current nuclear, and that is why the plans kept it at 50%. I'd prefer the flexibility issue was addressed, but that's a separate issue.
To understand how we got to the elevated share of nuclear, it's important to note the government's agencies' belief in what was going to happen with demand, and illustrate that against what did happen. I would argue 2011 is likely to come in below 2010 levels, so we see that in 2004 forecasts were too high, just as they were in 1989, when Ontario Hydro prepared “Providing the Balance of Power”. That document should have provided a warning as it wrongly predicted annualized growth of 2.2% over the 25 years to 2014. In 1989 Ontario's demand was 140.7 TWh, which is right about where we are heading in 2011.

The problem with this need to export is it has come at a time when the price of electricity is very depressed not only in Ontario, but in our primary export markets, which also saw demand peak in 2005 (although their declines have been less severe). I've been tracking, again as 12-month running totals, the difference between what export markets pay for Ontario electricity, and what Ontario residents/businesses would pay for the same amount of electricity. I've defined that as a subsidy. One notable from the first half of 2011 is this figure is at a new all-time high.

Reducing emissions has been the target of Ontario's electricity policies. Estimating emissions related to electricity generation, we see emissions have been reduced, and it does relate to the reduction of coal use.
Again the figures are relative to the peak demand year of 2005, and the chart indicates the variance to that (earlier the same dataset showed the relationship between declining demand and growing exports). These are my own lame estimates, of only CO2e based on 0.85MT/MWh for Coal, and 0.5 MT/MWh for gas. Unfortunately, this method matches up pretty well to the figures for Ontario emissions shown in Canada's GHG reporting. The reason for that is we don't actually measure emissions at the source, despite the increasing body of evidence that more intermittent generation (wind and solar) increases the emissions intensity of the natural gas back-up systems. GE is now targeting the performance, as back-up to intermittent sources, in its latest natural gas turbine designs, while across the world natural gas lobby groups are targeting governments to provide 'capacity' payments as they sell a blend of wind and gas supply.
It is in the relationship of intermittent, or 'green', generation sources, and natural gas back-up supply, that we have received the large price increases in Ontario, even as we have seen demand crumbling. Ontario could be cited as a world leader for its contracts with the big 5 CCGT installations that became operational since 2007, all of which basically receive capacity payment. Earlier this year a leading US electricity executive declared his company “almost as dependent on natural gas prices for earnings and growth as a gas exploration company.” Shortly thereafter another former executive was noting depressed prices were a market signal that no new generation should be built, and that gave way to a big push for 'capacity' payments, or subsidies, by the natural gas industry in North America; a call now being echoed across the Atlantic. If other jurisdictions are duped, Ontario will prove to have been a world leader as it figured out how to pay over $100/MWh for natural gas generation while less enlightened jurisdictions paid less than half that amount.
The other 'forward thinking' accomplishment of the first half of the year was the IESO's establishing methods to pay wind producers (and perhaps solar in the future) not to produce electricity. Because of the aggressive targets for adding wind - unneeded and unwanted - the IESO recognized we would increasingly have too much power, contracted by the inept OPA, and the threats to the grid required some action.
In fact they required the opposite of action.
They required the procurement of more supply to stop until there was a plan to avoid paying suppliers not to supply.
---
One stat I omitted when first posting, that I think is extremely relevant, is the number of hours of 'high' demand is falling consistently since 2005's peak. From a supply mix point of view, quite frequently nuclear is providing over 10000MW, hydro is capable of over 5000MW much of the day, and gas should be able to deliver another 5000MW (including over 4000MW of CCGT supply built in the past 4 years). The law of declining returns is kicking in extra hard as the coal use we are attempting to avoid is necessary fewer, and fewer, and fewer, hours almost every year.
---
One stat I omitted when first posting, that I think is extremely relevant, is the number of hours of 'high' demand is falling consistently since 2005's peak. From a supply mix point of view, quite frequently nuclear is providing over 10000MW, hydro is capable of over 5000MW much of the day, and gas should be able to deliver another 5000MW (including over 4000MW of CCGT supply built in the past 4 years). The law of declining returns is kicking in extra hard as the coal use we are attempting to avoid is necessary fewer, and fewer, and fewer, hours almost every year.
How does your analysis account for the retirement of Darlington and Pickering Nuclear Facilities and the highly likely Cost overruns that will be the outcome of any contracting process for new Nuclear?
ReplyDeleteThe analysis doesn't deal with those issues directly. I think that is where the direction is being steered, but let's be clear on the starting point. Demand is stagnant, supply is increasing and price is dropping - that is how a market requests supply be reduced.
ReplyDeleteUnrelated to the post, but to your comment, I think Darlington will be retired around 2050, and Pickering will likely operate as the refurb is done at Darlington. I'm less certain about Bruce B, but I've posted in the past 8 refurbished Bruce units and 4 at Darlington are likely sufficient. Within a year Bruce 1 and 2 should provide a better idea on the costing of that program - but what the government planned in the supply mix directive seemed realistic.
Scott... If you look into it Pickering is set for a refurbishment in 2014 and Darlington are to be retired around 2018. With regard to demand, the serious issue of Peak Oil will steer a return to electric vehicles that will drive demand to far exceed todays generating capacity. With regard to Price of electricity, the prices today are based on a fleet of generating sources that have long been paid for. Given that about 80% of Ontarios' generating capacity need replacement by 2020, the new cost of electricity will be based on New equipment, be it Nuclear, NatGas, Hydro or other renewables.
ReplyDeleteOPG's plan is to put some cash into Pickering to extend it until the Darlington refurbishment is done ( http://www.opg.com/news/releases/100211%20Nuclear%20Investment%20Strategy.asp ). I checked the OPA site and the contract looked to already exist for refurbishing units 3 and 4 at Bruce A.
ReplyDeleteBruce B is the blind spot for me.
80% replacement needs I just don't believe - I blogged on the Conference Board report to refute that. Off the top of my head, over 4000MW of CCGT was added since 2007, and the hydro plants will need work, but not replacement cost work. There's 10,000MW right there. As I stated, if the Bruce A and B refurbs complete without incident, we are at about 20000MW of capacity for 25 years or more, fairly cheaply.
I hope you are right on cars, but if that happens I think a breakthrough in storage (batteries) will have occurred, and that has implications for baseload too.
I do not drop a ton of comments, but I glanced through some
ReplyDeletecomments here "Ontario's Electricity System Halfway into 2011".
I do have a few questions for you if you do not mind.
Could it be simply me or does it give the impression like a few of the remarks look like they are written by brain dead individuals?
:-P And, if you are posting at additional places, I'd like to follow anything fresh you have to post. Would you make a list of the complete urls of your public pages like your twitter feed, Facebook page or linkedin profile?
Also visit my web site; Best registry cleaner
My web site - registry cleaner
all the time i used to read smaller content which as well clear their motive, and that
ReplyDeleteis also happening with this paragraph which I am reading at this time.
Here is my website :: airplane simulation games