Wednesday, April 4, 2012

GA'd Awful: Duncan Must Go


"Aren't you impressed to see so many people gather to hear you speak?" ... "No – because ten times as many would come to see me hanged."
"Nobody wants to create reliability problems, last of all us. I know who hangs on the lamp pole first."
If affordability problems are seen as reliability problems, Ontarians should be annoyed by the manner in which NDP Leader Andrea Horwath gives the Liberal government rope.

Friday, March 30, 2012

Week 12 Reporting: March GA Prediction

I have updated the weekly reporting to show the week of March 21 - March 27.

The news is in Hour 21(9pm) of Monday the 26th, which saw Ontario importing more electricity than it was exporting.  That's the first hour of 2012 that we have been a net importer.

Demand was down from last year (by about 1900MW per hour!), negative pricing occurred frequently, and steam bypass at Bruce B units not only occurred, but was sustained for days.

Wednesday, March 28, 2012

At Any Price: Wind as Negative Load, Not Generation

If wind is treated as ‘must take’ then it ought to be treated as negative load. The net load for the schedulable generators is then
Net = Actual – Wind

I thought that was a very elegant truth when I read it a couple of weeks ago, and fought the urge to write at length in support of the simple statement.  With the release of Ontario's feed-in tariff (FIT) review last week, celebrating 10700MW of renewables to be operational by 2015, I was more tempted to produce volumes illustrating the simple truth, and when I read Tom Adams' "The affliction for consumers is not a surplus of baseload generation but a surplus of take-or-pay generation, some of it stupidly expensive,"  I started pulling data and formatting graphs.

The term load is meant as the power consumed.  Generation must meet the consumption, so it is reasonable to view all the various generators as supply, and the demand as load.  Wind and solar contracted on a 'must take' basis, which the FIT contracts are, isn't meeting demand, but it is changing the load that must be met by other generators.

Baseload therefore refers, initially, to demand.  The first graph shows baseload as the minimum daily Ontario demand.  Between 2005, and 2011, the minimum dropped -on average 1574MW.  That, coincidentally, is about the capacity of nuclear supply due to return as Bruce 1 and 2 return to service (I think the contracts were negotiated in 2005).

At any price: Reviewing Ontario's FIT review.

Last week the Ontario government rushed out FIT review.  The review was reported to have been with the minister only 3 days, but that was enough to release it the same day the Opposition Leader's bill to abolish the program was voted on, and defeated, in the provincial legislature.  That was a very quick turnaround for a ministry that has been sitting on the Integrated Power System Plan submitted by the same body - the Ontario Power Authority (OPA) - prior to last fall's election.

I disagree with the FIT program for a number of reasons - economic, political/social, and environmental (reasons have been explored in previous blog posts one, two, and call this three).  I'll again briefly review how the program increases pricing, how it kills jobs, and how it can only  increases emissions.  I'll also look at the supporters of the policy, and what they have in common that enables them to argue an unsubstantiated positions successfully.

Wednesday, March 21, 2012

Ontario's Sick Electricity Sector Symptom of the Week: Paying gas generators not to generate

It will be a couple of days until I'll update the weekly reporting, but the generator data is set, and much of the pricing data.  In week 11 (March 14th - 20th) the frequency of steam bypass maneuvers at Bruce B increased, but we also see another supply curtailment method used over the weekend - the idling of non-utility generators (NUGs).  Over the weekend Ontario appears to have been simultaneously paying one of Canada's power giants, TransAlta, not to produce with natural gas at co-generation facilities while purchasing the output from their intermittently generating wind properties.

Curtailment of the NUGs is usually for a number of days.  One of the reasons is contracts that predate the current electricity system's structure.  The contracts were with Ontario Hydro, and when that ceased to exist they were transferred to the Ontario Electricity Financial Corporation (OEFC).  Operationally, that means the shutdowns need to be scheduled in advance.  In this instance, the surplus baseload generation (SBG) reporting indicated far too much supply over the weekend, and NUG's were curtailed, by about the same wattage as one of Pickering's units, from late Friday night to the demand ramp up Monday morning.  
NUG contracts are private, but estimated above $100/MWh.

Friday, March 16, 2012

Nuclear Units Sidelined as Demand, and Price, Drop: Week 10 Report

Week 10 reporting, for Wednesday March 7 - Tuesday March 13, has replaced week 9's figures in my version of weekly reporting.  
The record low pricing for a single day occurred on Sunday, and the weighted average price for the week, $11.74, was the lowest weekly average price since 2009.
Predictably, the depressed pricing corresponded to a record week for wind output.

Thursday, March 15, 2012

The Lies of March: ENGO’s Coordinated Dishonesty Props up McGuinty


By the end of 2014, Ontario will be the first jurisdiction in the world to replace dirty coal-fired generation with more sustainable alternatives such as wind, solar and bioenergy -- the equivalent of taking seven million cars off the road. This is the single largest climate change initiative being undertaken in North America and will lead to savings of $4.4 billion a year in health care, environmental and financial costs.
-“Ontario Shutting Down Two More Coal Units” news release, December 1, 2011

This is one of the more recent quotes deliberately attributable to the Ontario government.  Most statements regarding coal have their foundation in a document from April 2005, “Cost Benefit Analysis: Replacing Ontario’s Coal-Fired Electricity Generation,” which was prepared by DSS Management consultants.  The quoted news release displays neither an understanding of the document, nor an attempt at understanding.  The figure above includes the energy based on 2004 generation and costs - if if were possible to replace 2004’s roughly 27.6TWh of coal generation with wind turbine output, contracted at $135/MWh, the cost would be $3.725 billion, plus the significant environmental and heath costs of that source.  There are no savings even if the report is accepted as gospel.

The figure people attempting honesty quote are found in Table I-4 of the report, and that figure is roughly $3 billion a year in ‘Health Damages.’

Tuesday, March 13, 2012

Spooning for McGuinty - battling an Act of Hudak

Ontario PC leader Tim Hudak introduced a bill to eliminate the Feed-in Tariff (FIT) Program and restore local control over local issues; the "The Affordable Energy and Restoration of Local Decision Making Act."  It must be good, judging by the weakness of the arguments against it.  The Canadian Wind Energy Association (CanWEA) issued a news release titled "Proposed Act would create significant economic uncertainty, put local jobs at risk."  If the field of economics had Razzie awards, the CanWEA release would be in it's hall of shame.