- electricity prices soared in the second quarter;
- OPG fell behind schedule on it's Darlington refurbishment - and started morphing back into a fossil fuel generator;
- the IESO removed the incremental capacity auction leg from its wobbly market renewal stool.
The useful structures planned during the previous government are falling apart during the implementation stage, and the current Minister of Energy, et cetera, has appeared - well, infrequently. It's still early in the sophomore year for the Honourable Greg Rickford, but he's shaping up to be the worst energy minister since Brad Duguid.
Duguid could have saved Ontarians billions if he'd stuck to his druthers and implemented the solar rate cut the Ontario Power Authority decided on in 2010, but he didn't. He succumbed to lobbying from an industry not to reduce rates, and eventually, as those high-priced contracts entered service, Ontario became a global laughingstock for contracting solar capacity at an average price well above $400/megawatt-hour (MWh).
A feed-in tariff (FIT) contract for the 300 MW Henvey Inlet wind project was announced eight-and-a-half years ago on February 24, 2011. From the standard FIT contract during February 2011 (version 1.4):
2.5 Milestone Date for Commercial Operation
The Supplier acknowledges that time is of the essence to the OPA with respect to attaining Commercial Operation of the Contract Facility by the Milestone Date for Commercial Operation set out in Exhibit A. The Parties agree that Commercial Operation shall be achieved in a timely manner and by the Milestone Date for Commercial Operation.The date for commercial operation was generally 3 years from the contract date. Later it was extended to 4 years for many contracts.
Henvey Inlet, at some point, received extra special consideration and it's date for commercial operation was extended to February 25, 2018 (according to IESO contract list). Today being August 26, 2019, is more than 1 and half years from the date for commercial operation.
Section (9.1), "Events of Default by the Supplier", includes:
(j) The Commercial Operation Date has not occurred on or before the date which is 18 months after the Milestone Date for Commercial Operation, or otherwise as may be set out in Exhibit A.